YOU CAN DOWNLOAD 200+ SUBJECTS PDF BOOK FOR COMPETITIVE EXAMINATIONS
Time And Work
Question 51 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
10 1/2 | |
5 days | |
6 days | |
10 days |
Question 51 Explanation:
\begin{align} & \left( {{\text{B + C}}} \right){\text{'s}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} \cr & = \left( {\frac{1}{9} + \frac{1}{{12}}} \right) = \frac{7}{{36}} \cr & {\text{Work}}\, {\text{done}}\, {\text{by}}\, {\text{B}}\, {\text{and}}\, {\text{C}}\, {\text{in}}\, {\text{3}}\, {\text{days}} \cr & = \left( {\frac{7}{{36}} \times 3} \right) = \frac{7}{{12}} \cr & {\text{Remaining}}\, {\text{work}} \cr & = \left( {1 - \frac{7}{{12}}} \right) = \frac{5}{{12}} \cr & {\text{Now}}, \, \frac{1}{{24}}\, {\text{work}}\, {\text{is}}\, {\text{done}}\, {\text{by}}\, {\text{A}}\, {\text{in}}\, {\text{1}}\, {\text{day}} \cr & {\text{So}}, \, \frac{5}{{12}}\, {\text{work}}\, {\text{is}}\, {\text{done}}\, {\text{by}}\, {\text{A}}\, {\text{in}} \cr & \left( {24 \times \frac{5}{{12}}} \right) = 10\, {\text{days}} \cr\end{align}
Question 52 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
18 days | |
6 days | |
4 days | |
8 days |
Question 52 Explanation:
\begin{align} & {\text{Ration}}\, {\text{of}}\, {\text{rates}}\, {\text{of}}\, {\text{working}}\, {\text{of}}\, {\text{A}}\, {\text{and}}\, {\text{B}} \cr & = 2:1 \cr & {\text{So, }}\, {\text{ratio}}\, {\text{of}}\, {\text{times}}\, {\text{taken}} = 1:2 \cr & {\text{B's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} = \frac{1}{{12}} \cr & \therefore {\text{A's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} \cr & = \frac{1}{3};\, ({\text{2times}}\, {\text{of}}\, {\text{B's}}\, {\text{work}}) \cr & \left( {{\text{A + B}}} \right){\text{'s}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} \cr & = \left( {\frac{1}{6} + \frac{1}{{12}}} \right) = \frac{3}{{12}} = \frac{1}{4} \cr & {\text{So, }}\, {\text{A}}\, {\text{and}}\, {\text{B}}\, {\text{together}}\, {\text{can}}\, {\text{finish}}\, {\text{the}} \cr & {\text{work}}\, {\text{in}}\, {\text{4}}\, {\text{days}}{\text{.}}\, \cr\end{align}
Question 53 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
A complete 7/10 of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?
12 2/3 days | |
10 1/2 days | |
8 1/4 days | |
13 1/3 days |
Question 53 Explanation:
7/10 part of work has been completed by A in 15 days. Then,
Rest work = 1 - (7/10) = 3/10 part.
Given, That 3/10 part of the work is completed by A and B together in 4 days. Means,
(A+B) completed the 3/10 of work in 4 days.
So, (A+B)'s 1 day's work = 3/(10*4) = 3/40;
Hence,
(A+B) can complete the work in 40/3 = 13(1/3) days.
Question 54 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
6 days | |
7 days | |
8.1 days | |
5.1 days |
Question 54 Explanation:
X completes 1/3rd in 4 days = 33.33 % job in 4 days.
X One day work = 8.33%
Y one day work = 5.55% [As he complete 1/6 job = 16.66 % job in 3 days]
Z one day work = 10%
Work done in 3 days by X, Y and Z
= 25 + 16.66 + 30 = 71.66 %
Remaining work will be done by Y in,
28.33/5.55 = 5.1 days.
Question 55 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?
10 days | |
20 days | |
25 days | |
24 days |
Question 55 Explanation:
Assume work to be done 100%.
First case,
A + B = 100/5 =20% work done per day -------- (1)
Second case,
2A + B/2 = 100/4 = 25% work done per day ------ (2)
On solving equation (1) and (2), we get
A = 10 days.
There are 55 questions to complete.
