Time and work questions

YOU CAN DOWNLOAD 200+ SUBJECTS PDF BOOK FOR COMPETITIVE EXAMINATIONS

CLICK HERE TO DOWNLOAD

Time And Work

Question 31 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
A
50
B
35
C
40
D
45
Question 31 Explanation: 
\begin{align} & {\text{Let}}\, {\text{1}}\, {\text{man's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} = x\, {\text{and}} \cr & {\text{1}}\, {\text{woman's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} = y \cr & {\text{Then}}, \, 4x + 6y = \frac{1}{8}\, {\text{and}} \cr & \, \, \, \, \, \, \, \, \, \, \, \, \, \, \, \, \, 3x + 7y = \frac{1}{{10}} \cr & {\text{Solving}}\, {\text{the}}\, {\text{two}}\, {\text{equations, }}\, {\text{we}}\, {\text{get}} \cr & x = \frac{{11}}{{400}}\, \, , \, \, \, y = \frac{1}{{400}} \cr & \therefore {\text{1}}\, {\text{woman's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} = \frac{1}{{400}} \cr & \Rightarrow {\text{10}}\, {\text{women's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} \cr & = \left( {\frac{1}{{400}} \times 10} \right) = \frac{1}{{40}} \cr & {\text{Hence, }}\, {\text{10}}\, {\text{women}}\, {\text{will}}\, {\text{complete}}\, {\text{thw}}\, {\text{work}}\, {\text{in}}\, {\text{40}}\, {\text{days}} \cr\end{align}
Question 32 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?
A
6:20 PM
B
6:42 PM
C
6:36 PM
D
6:30 PM
Question 32 Explanation: 
1st Method:

Whenever, workers are working alternatively on one work, we take 2 as 1 unit.

In this case, we take 2 hours as 1 unit.

Part of the field moved by Ganga and Saraswati in 2 hours (1 unit) = 1/8 + 1/12 = 5/24;

Time taken to complete the work,

= 1/(5/24) = 24/5 unit of time;

Then actual time taken by them to complete the work,

=2 * 24/5 = 9.6 hours.

The work starts at 9 a.m. then it will complete at 6:36 pm.

2nd Method:

% of the field moved by Ganga and Saraswati in 2 hours (1 unit),

= [(100/8)% + (100/12)%]

= 12.5 + 8.33

= 20.83%; Time taken to move the whole field,

= 100%/20.83%

= 4.8 unit of time;

Hence, actual time = 2*4.8 = 9.6 hours.

Question 33 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:
A
60
B
51/5
C
65/4
D
93/3
Question 33 Explanation: 
Let x be the required number of days.

Given,

12 men and 12 women can complete a work separately in 14 days and 21 days respectively.

Then,

12 man's 1 day work = 1/14

And,

12 women's 1 day work = 1/21

Then,

12 women's 3 days work = 3/21 = 1/7

The remaining work = 1 - 1/7 = 6/7

Man's group leaves 3 days before the completion of work.

That is, they were working together for x-3 days.

Thus, we have 1/7 work left to be done in last 3 days by the women's group. This also means 6/7 th of work has been done by both the groups (before men left).

Now, (12 men + 12 women)'s 1 day work = 1/14 + 1/21 = 5/42.

i.e., 5/42 work is done by 2 groups in 1 day.

So, 6/7 of work is done by 2 groups together in (42/5)(6/7) = 36/5 days.

As we know, women's group will work to

Question 34 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A and B can do a job together in 7 days. A is 1 3/4 times as efficient as B. The same job can be done by A alone in :
A
11 days
B
12 1/4 days
C
16 1/3 days
D
9 1/3 days
Question 34 Explanation: 
\begin{align} & \left( {{\text{A's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}}} \right){\text{:}}\left( {{\text{B's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}}} \right) \cr & = \frac{7}{4}:1 = 7:4 \cr & {\text{Let}}\, {\text{A's}}\, {\text{and}}\, {\text{B's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}}\, {\text{be}} \cr & 7x\, {\text{and}}\, 4x\, {\text{respectively}} \cr & {\text{Then}}, \, 7x + 4x = \frac{1}{7} \cr & \Rightarrow 11x = \frac{1}{7} \cr & \Rightarrow x = \frac{1}{{77}} \cr & \therefore {\text{A's}}\, {\text{1}}\, {\text{day's}}\, {\text{work}} \cr & = \left( {\frac{1}{{77}} \times {\text{7}}} \right) = \frac{1}{{11}} \cr\end{align}
Question 35 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?
A
NITian is 33.33% less efficien
B
IITian is 20% less efficient
C
IIT is 33.33% less efficient
D
NIT is 25% less efficient
Question 35 Explanation: 
Let E1 and E2 are the working efficiency of each student of IIT and NIT per hour respectively.

Using work equivalence method,

4 *10 *60 *E1 = 5 *8 *80 *E2

E1/E2 = 4/3

As, 3E1 = 4E

% less efficient of NITians = (1*100)/4 = 25%

Thus, each engineer from NIT is 25% efficient than that of IIT.

There are 35 questions to complete.

Leave a Reply

Your email address will not be published. Required fields are marked *