Time And Work
Question 1 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
1200 | |
4500 | |
7200 | |
2400 |
Quantity of water emptied per hour = 4 * 60 = 240;
Thus, 10% = 240 liter;
Hence, capacity of water,
100% = 240*100/10 = 2400 liter.
Question 2 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
9 days | |
10 days | |
6 days | |
5 days |
(A+B)'s one day's work = 1/3 part;
(A+B) works 2 days together = 2/3 part;
Remaining work = 1-(2/3) = 1/3 part;
1/3 part of work is completed by A in two days;
Hence, one day's work of A = 1/6;
Then, one day's work of B = 1/3 - 1/6 = 1/6;
So, B alone can complete the whole work in 6 days.
2nd method:
(A+B)'s one day's % work = 100/3 = 33.3%
Work completed in 2 days = 66.6%
Remaining work = 33.4%;
One day's % work of A = 33.4/2 = 16.7%;
One day's work of B = 33.3 - 16.7 = 16.7%;
B alone can complete the work in,
= 100/16.7 = 6 days.
Question 3 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
12 days | |
10 days | |
15 days | |
8 days |
Question 4 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
15 | |
18 | |
16 | |
25 |
Question 5 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER] |
120 days | |
72 days | |
100 days | |
80 days |
(x +11) *50 = (x +15) *45
→ x = 25
Thus, Total quantity of oil,
= (25 +11) *50
= 1800
Hence, required number of days,
= 1800/25 = 72 days.